Construction Duties to Optimize IT Consistency in New Five Guys Build
Timeline
Manager Desk Install
Internet Install
Manager PC plugged into the Bell/Telus router & email Thomas
Open the SonicWall and place on the middle shelf, as shown below
POS install
Manager Desk
Please note the location of each device
The Bell/Telus/Rogers hardware should be mounted on the wall, out of reach
The music system can go on the top or middle shelf, depending on how deep the shelves are and the length of each shelf. Ideally the top shelf is where it should go.
The printer and computer monitor can be moved around depending on the needs of the GM.
Power for all devices is on the top shelf, using one or two large surge protectors. These may need to be purchased if there are none on hand.
NETWORK Map
Patch Panel
Each restaurant must have a patch panel installed and mounted to the wall next to the manager desk.
Each connection needs to be labeled on both ends
The colouring of each cord is important for each device, our POS provider should be ensuring this is correct.
Manager Desk Patch Panel
Click for Full Screen
Under the Front Counter POS
Click for Full Screen
Pin Pads
The pin pads should be mounted in front of the POS and shown below.
There is a pin inside the stand that needs to be punched out so the power cable can be fed through and then the pin can be put back through
The stand comes with an adhesive bottom. Remove the red tape from the bottom of the stand and mount it over the pre-drilled hole in the counter. The hold in the counter should allow access to below the POS on the other side.
Click for Full Screen
Click for Full Screen
Click for Full Screen
Mounting
Please mount the Compliance Mate to the wall if possible, as shown below.
Click for Full Screen
Please mount the surge protector to the wall or under the counter, as shown below. Mounting them to the wall is ideal but this depends on shelving and space requirements. It is important these do not get left on the floor.
Click for Full Screen